How to Run a Two-Week Proof of Concept for an Ontology Platform

A practical PoC plan for an ontology-based AI data platform: one owned business question, synthetic data first, a fixed delivery sequence, written acceptance criteria and a go/no-go review.

Structure the proof of concept (PoC) around one business question that has a named owner, written acceptance criteria and a limited scope, and run it in a fixed order: synthetic data, then a draft ontology, then a reviewed change, then a task a business user can verify. The sequence below follows DataFocus's published guidance for OT, and the two-week calendar around it is our suggestion, not a DataFocus requirement. It works the same way for other ontology platforms, because the failure modes of a PoC are mostly about scope and acceptance, not about the tool.

Why do AI PoCs stall in the first place?

MIT's Project NANDA reported in July 2025 that only 5% of organizations reached production with enterprise-grade GenAI tools, after 60% evaluated such tools and 20% reached pilot. The same report says its figures are "directionally accurate" and rest on interviews rather than audited company reporting, so treat the exact percentages with care. Its qualitative finding is the useful part for a PoC planner: the authors attribute stalls mainly to tools that do not learn and do not integrate well into workflows.

That points to what a PoC must prove. It is not "the model can answer a question". It is "the definitions, the data and the permissions for one real task hold together, and a person can check the result."

Step 1: Pick one business question with an owner

DataFocus's product brief suggests starting with a business question that has data, policy documents and a clear owner, and gives order delivery and purchase approvals as examples. Its getting-started guidance adds that you should define the task, its business owner, the acceptance criteria and the permitted scope before anything else.

Write this on one page before day one:

  1. The question, in the owner's words ("Which open orders are at risk of missing the delivery date?").
  2. The owner, a named person who can say whether an answer is right.
  3. The tables and policy documents the question depends on.
  4. The permitted scope: which systems, which fields, read-only or not.
  5. The acceptance criteria (see Step 4).

A useful test of the question is whether its key term needs a definition. In DataFocus's published delivery demo, "delivery" means production is complete and ready for handover at the factory, excluding transport and customer acceptance. Under that definition, a forecast of two days late is a predicted risk, not a breach, and a missing production forecast produces "not enough information" rather than "on track". The same guidance warns against equating production completion, dispatch and customer acceptance without confirmation. If your owner cannot settle a definition like that, the PoC will surface the gap, which is a legitimate result.

Step 2: Start with synthetic data and demo cases

DataFocus's guidance is to start with synthetic data and not to enter customer information into the interactive demos. The homepage demos run on simulated data in the browser: demo actions change data only in the current page and reset on refresh, no server workspace is created and conversations are not saved. The case pages are published demo scenarios, and independent case packages can be imported into your own DataFocus environment.

For an integrator this gives a low-risk first week:

  • Walk the owner through the closest demo scenario to agree on what "good" looks like.
  • Build a synthetic copy of your client's tables with the same shapes and awkward cases (missing forecasts, duplicate customers, changed policies) but no real records.
  • Keep real credentials and records out of the environment until the scope document is signed off.

Reuse also matters for your business model. According to DataFocus's building guide, definitions, mappings, required scopes and tests can be reused across projects, while customer records, credentials, private documents and source access rules cannot, and identities and permissions must be remapped in each new environment. Design your PoC artifacts with that split in mind.

Before connecting real data, run the deployment preparation checklist. It covers usage scope, operating system and architecture, capacity, data authorization, model choice, data egress and backup ownership. DataFocus OT is self-hosted, administrators configure the large-language-model service, and with an external model the customer should confirm what is sent to it under its data policy. System requirements and supported platforms are listed in each edition's release notes; beyond that, plan resources around data volume, concurrency and model requirements.

Step 3: Follow a delivery sequence: inspect, confirm, draft, diff, test

DataFocus's building guide suggests this order: inspect version and capabilities, inspect sources, confirm meaning, draft, review the diff, test, obtain authorization, publish and read back, then verify a business task. It also says to read the actual tool schema from the instance before using it with a coding agent, since the catalog depends on your instance.

A two-week calendar that fits that order (our suggestion, illustrative, not run):

DaysWorkOutput
1-2Scope page, owner sign-off, version and capability inspectionSigned scope, instance notes
3-4Source inspection on synthetic data, confirm meanings with the ownerDefinitions list with open questions
5-6Draft ontology: tables, relationships, the definitions that were confirmedDraft and diff
7-8Review the diff, test against the question setTest results, issues
9-10Authorization and publish, read backPublished version, read-back record
11-12Business user works the task; optionally authorize an AI agentTask verified by the owner
13-14Evidence pack, go/no-go reviewDecision

The homepage's second demo shows what a good draft step looks like, on synthetic data. A coding agent inspects sources and proposes a draft with four object types, three relationships and one definition to confirm. It stops and asks when a definition is unclear, reports "Source writes 0 · access unchanged", and cannot approve its own change, because publishing needs someone with authority. Use that as a model for your own checks: the agent should ask, not guess, and a person with authority should publish.

The guidance on writes is also concrete. Changes go through draft, diff, validation, approval, commit and read-back; approval applies to a specific plan and base version and must be confirmed again if either changes. Add repeated submissions, version conflicts and recovery to your test list before you trust it.

Step 4: Acceptance criteria and evidence to collect

Write criteria the owner can mark pass or fail, and decide up front what evidence supports each one. A starting set:

CriterionEvidence to keep
The answer to the owner's question matches the owner's expected result on a fixed question setThe question list, expected answers, actual answers
Terms with business definitions behave as defined, including "not enough information" casesTest cases per definition, results
A change cannot take effect without a named approverThe recorded diff and approver
A changed version requires fresh approvalA test where the base version changes after approval
Permissions follow your existing accounts and tenant boundariesA check of what each role can see in queries, relationships, summaries, caches, logs and exports
The agent did not write to sourcesThe "source writes" report and source-side logs
The owner can trace an answer to sources and definitionsA sample of answers with sources and returned scope

The permission row follows DataFocus's docs guidance to use existing enterprise accounts, tenant boundaries and resource permissions and to check server-side visibility for those places. The traceability and change-record rows relate to what the homepage describes: each call records sources, definitions and returned scope, and each change records before and after, the diff and who approved it.

Note what is deliberately missing: performance numbers. DataFocus publishes none, so do not copy any into your plan. If speed or concurrency matters to the client, define your own load case, run it on the client's sizing and record the result as your own measurement.

Step 5: Go/no-go review

Hold the review with the owner, using the evidence pack, and keep the decision rule short:

  • Go: every criterion passes, open definitions are resolved or explicitly deferred, and the owner confirms the verified task is one they would use.
  • Go with conditions: criteria pass but the permission or write checks need work in a named, dated step.
  • No-go: a definition could not be agreed, or an unapproved change could take effect.

After a go, the product brief's suggested path is to bring business users onto the first ontology, authorize an AI agent next, and then move to the next business area. That ordering keeps the second PoC from becoming a repeat of the first.

When this plan is not the right fit

Two weeks assumes the owner is available and the sources are reachable. If the data sits behind approvals that take longer than two weeks, spend the time on the synthetic phase and extend the calendar rather than skipping the scope page. If the question has no single owner, such as a goal that spans several departments, split it first. Also confirm which edition you are evaluating: DataFocus lists ETL and automated machine learning for Heavy and not for Flash, so a PoC that needs them has to run on Heavy.

Next step

Read DataFocus's getting-started guide and building guide for the full wording of the sequence, and install either edition from the download page or the GitHub repositories for OT Flash and OT Heavy, where the installers and release notes are published.